Kashirskoye highway intersections with avenues Proletarian Andropov and completed in July

In Moscow in July 2013 will complete the construction of tunnels at the intersection of the Kashirskoe highway with Proletarsky Prospekt and Prospekt Andropova. As the press service of the Department of construction, currently working on the construction of the two tunnels is more than 70%. Tunnel works on the device of pedestrian crossings, relocation of utilities, reconstruction of electric networks, communication networks and street lighting.

After completion of the two-level transportation will provide the traffic light-less traffic on the section of the main course Kashirskoe highway, and exits with Proletarsky Prospekt and Prospekt Andropova on Kashirskoye highway in the direction of the centre and towards the area, and exits with the Kashirskoe highway on proletarian Avenue when moving from the center and on Prospekt Andropova when moving from the area, as well as a traffic light-less movement between Proletarsky Prospekt and Prospekt Andropova in both directions.
Work is carried out on the project of reconstruction of the Kashirskoe highway from Moscow ring road (MKAD) to Warsaw highway. To complete their plan in July 2013.
"This is one of the most difficult and busy intersections on Kashirsky highway, because Proletarsky Prospekt and Prospekt Andropova adjacent to the highway from different sides on the destruction of 100 m from each other, and the presence of traffic lights makes the traffic situation. After completion of the tunnel construction and reconstruction of highways will significantly increase the road capacity», - said the head of the construction Department Andrey Bochkarev.